How Will Sound Transit Manage Future Service Disruptions with Two Overlapping Lines?

Stephen Fesler - November 28, 2023
Riders wait on University Street station platforms during an unanticipated service disruption. (Ryan Packer)

With another “Future Ready” maintenance project coming down the pike in January, it raises a big question for the future: What should riders expect when Sound Transit needs to do planned or emergency maintenance work in the downtown tunnel and elsewhere in the Link system?

Starting in late 2025 or 2026, riders can expect the Link 1 and 2 Lines to operate through the downtown tunnel for regular service. This will effectively double the number of trains running through it, but it will also increase the complexity of operations.

After ST2 is built out, Line 1 will run from Federal Way to Lynnwood and Line 2 will run from Redmond to Lynnwood via Downtown Seattle.
Sound Transit plans to open Federal Way Link in 2026, completing the ST2 rail buildout. Both Line 1 and Line 2 will operate in the Downtown Seattle Transit Tunnel until Ballard Link opens (circa 2039) and Line 1 switches to the new tunnel added with that project. (Sound Transit)

With maintenance events already being a delicate matter with just one line, adding another into the mix and increasing frequency seems all but sure to gum things up. Sound Transit doesn’t have a clear cut answer to how the agency will deal with future maintenance and emergency repair projects because every situation is unique, but it’s hard to see it being any better for riders without substantial improvements to infrastructure and agency operational strategies.

Come mid-January, Sound Transit will once again run single-tracking operations in the downtown tunnel to support critical maintenance work. Service in the tunnel will be about 26-minute intervals in each direction and extra service will be layered on portions of the system outside the tunnel to provide cumulative 13-minute frequency. On weekends, the downtown tunnel will fully close for more complex maintenance work.

How Link 1 Line service will run during the upcoming January-February planned maintenance work period. (Sound Transit)

It stands to reason that if the upcoming service disruption were happening in a two-line environment using the same strategy, through service in the downtown tunnel might be something closer to one 1 Line and one 2 Line trip per hour. One 2 Line trip means just one trip between Seattle and the Eastside per hour, and with low through-train options for riders to choose from, loads on trains and platforms would likely be very unbalanced and overloaded. It would be a systemwide catastrophe.

Sound Transit would probably pursue another strategy, perhaps by trying to time and platoon 1 Line and 2 Line trips together in the same direction through the downtown tunnel so as to get closer to the half-hourly frequency level. But that itself wouldn’t be easy to do and illustrates just how challenging and tenuous the tunnel could be without major changes.

To be sure, Sound Transit has made some strategic enhancements to the downtown tunnel.

Last year, the agency went through a process of sectioning the overhead catenary wire system, which provides power to light rail vehicles, into quadrants within the tunnel. Dividing the system into quadrants allows the agency to strategically turn off power to portions of the tunnel being worked on and run trains to more tunnel stations when doing so. Sound Transit previously had to be more selective about which stations could be used during a partial single-tracking event.

The diagram shows a partial single-tracking event in the downtown tunnel with forced transfers at Pioneer Square station to continue journeys on the Link 1 Line during summer maintenance work to repair sinking tracks in SoDo. (Sound Transit)

Nevertheless, the Achilles’ heel of the downtown tunnel is the inability of trains to switch tracks within it, barring a section immediately northeast of Westlake station platforms (the other nearest crossover tracks are at Stadium, Judkins Park, and University of Washington stations). That reduces Sound Transit’s ability to navigate around temporary construction zones or stalled vehicles, forcing the agency to choose from more blunt strategies. Those include using a low-frequency, blended through-service on a single-track, running a Link train as a shuttle between both ends of the downtown tunnel, or running two trains partially through the downtown tunnel to a common station with a forced transfer. All of those have their problems and seem set to be compounded when Link does get its two full lines.

A map shows downtown light rail stations and tracks.
A map shows downtown light rail stations and tracks.

A strategy that could significantly ameliorate this, however, would be installation of permanent crossover tracks (known as switches) throughout the downtown tunnel. Installing crossover tracks at the tunnel stations themselves would be the least expensive method to help trains navigate around obstacles in the tunnel. But doing so could affect service at a station where crossover tracks are in use if Sound Transit didn’t authorize a special maneuver to pull into the station’s platform, reverse the train, and then proceed forward onto and over the crossovers to switch tracks. Alternatively, the agency could select portions of the tunnel tubes between stations for crossover tracks, though that would require a more costly approach by excavating space from interior walls to lay tracks.

The addition of a second downtown transit tunnel with the Ballard Link Extension will certainly open up new options to deal with maintenance and service disruptions, carrying some of the load when the existing tunnel needs repairs. But with the specter of planning delays, Ballard Link isn’t scheduled to open until 2039 at the earliest. That means Sound Transit will need a solution for the next 15 or so years.

Another issue that Sound Transit will have to contend with is planned maintenance and unexpected service disruptions elsewhere in the Link system.

In the summer, the agency carried out several phases of maintenance work to repair sinking tracks in SoDo and replace platform tiles at Othello and Rainier Beach stations. Service impacts from the work was fairly severe with systemwide frequency reduced to every 20 minutes during track repairs and every 15 minutes during tile replacement. The agency blamed lower-than-planned frequencies on a variety of factors, including signal systems when operating on a single track in the reverse direction. Trains also had to operate on a long 1.5-mile segment of single track since crossover tracks are only located north of Othello station and south of Rainier Beach station. Clearing that whole segment takes time, especially with two station stops along the way.

The diagrams show how single-tracking was put into service in the Rainier Valley over the summer during tile replacement work at Othello and Rainier Beach stations. (Sound Transit)

Sound Transit will invariably have many substantive maintenance work and unexpected service disruptions (e.g., motorists crashing into Link trains in the Rainier Valley) that necessitate single-tracking outside the downtown tunnel. Minimizing their impacts should be a bigger priority than they have been in the past. Some key questions that policymakers and agency staff should be asking and answering, include:

  • Could Sound Transit take actions that further limit the severity of single-tracking events and improve system operations through strategic infrastructure investments?
  • Does a whole line have to suffer a significant loss of frequency or could the agency maintain normal frequencies outside construction and service disruption zones?
  • And, can more maintenance work be shifted to late-night periods or when the system is closed to limit rider impacts?

If the scope and frequency of planned maintenance single-tracking events continues like it has with 10-day or 20-day service disruptions, it’s hard to imagine riders tolerating it like they have in the past with impacts spreading widely across a system soon to grow to 57 miles and eventually to 116 miles. That’s why Sound Transit should have to answer how the agency can and will limit severe service disruptions before the Lynnwood Link, East Link, and Federal Way Link Extensions even open, not when they’re poised to imminently happen in a post-Sound Transit 2 expansion environment.

Light Rail Tunnel Maintenance to Disrupt Service Starting in January
‘Future Ready’ repairs will disrupt light rail service from January 13 to February 4, but Sound Transit is trying a new strategy to reduce impacts. Sound Transit plans to move ahead with needed maintenance work in the downtown tunnel early next year. It’s one of the last phases of “Future Ready” maintenance and preparation work … Continue reading Light Rail Tunnel Maintenance to Disrupt Service Starting in January
Link Light Rail Resumes Normal Service Saturday, Ending Maintenance Disruptions
Sound Transit will nearly double frequencies on Link light rail with the completion of maintenance work. Sound Transit announced normal light rail service will resume on Saturday morning as it wraps up tile work at the Othello and Rainier Beach station platforms two days ahead of schedule. During peak hours, Link normally runs every eight … Continue reading Link Light Rail Resumes Normal Service Saturday, Ending Maintenance Disruptions
Light Rail Running at Reduced 15-Minute Frequencies Until Mid-September, Frustrating Riders
Riders are feeling the pain as maintenance work continues to impact Link train frequencies. Last week, Sound Transit managed only 20-minute frequencies during work to repair sinking tracks in SoDo. That work wrapped on Monday but the agency quickly pivoted to repairing tiles on station platforms at Othello and Rainier Beach — work that is … Continue reading Light Rail Running at Reduced 15-Minute Frequencies Until Mid-September, Frustrating Riders
Late Summer ‘Future Ready’ Maintenance Leads to Link Service Disruptions
Light rail won’t operate between SoDo and Capitol Hill on August 12 and 13, with a service gap bus bridge instead. A series of single-tracking disruptions will follow. More planned service disruptions are coming to the Link light rail. On Thursday, Sound Transit CEO Julie Timm announced upcoming service disruptions to address track quality issues … Continue reading Late Summer ‘Future Ready’ Maintenance Leads to Link Service Disruptions
Next Rounds of ‘Future Ready’ Sound Transit Fixes Promise Less Disruption
Sound Transit has additional Future Ready maintenance and repair projects teed up for this year and next. In a briefing, agency staff outlined planned works and lessons learned from previous ones. Julie Timm, the new Sound Transit CEO, essentially issued a mea culpa for the agency on the Columbia City tile replacement kerfuffle and said … Continue reading Next Rounds of ‘Future Ready’ Sound Transit Fixes Promise Less Disruption
Sound Transit Lessens Pain For Initial ‘Future Ready’ Maintenance Projects
On Tuesday, Sound Transit announced it would be maintaining 10-minute light rail frequencies north of Stadium Station during its upcoming “Future Ready” maintenance projects. This major positive change stemmed from pressure by transit advocates (including The Urbanist) concerned with the rider impact of the earlier plan reducing Link service to 20-minute frequencies throughout the entire … Continue reading Sound Transit Lessens Pain For Initial ‘Future Ready’ Maintenance Projects