Sea-Tac Airport Sets Passenger Record, Plans Next Phase of Expansion Projects

Stephen Fesler - February 15, 2025
An Air Tahiti Nui plane taxis at Seattle-Tacoma International Airport. (Stephen Fesler)

Growth at Seattle-Tacoma International Airport (SEA) continues at a fast clip with new service, expanded and improved facilities, and booming passenger volumes. The airport has fully emerged from the pandemic period with a new record of 52.6 million passengers in 2024, besting 2019’s record of 51.8 million. Passenger volumes were up about 3.5% from 2023 despite the grounding of Boeing 737 MAX 9’s early in the year, due a midair door plug blowout. 

The Port of Seattle projects another year of increased passenger volumes, rising another 1.7% to 53.5 million in 2025.

Domestic passenger volumes were slightly above 2019 levels with about 46 million, a 0.1% increase. But the bulk of increased passenger volumes has come from international travel, rising 15% from 2019 levels to around 6.6 million passengers. 

Airport passenger volumes have consistently grown since the Great Recession, except for the immediate period following the Covid-19 pandemic. (Stephen Fesler)

2024 saw the addition of eight new international connections with service to Taipei–Taoyuan (STARLUX Airlines, China Airlines, and Delta Airlines), Munich (Lufthansa), Chongqing (Hainan Airlines), Toronto–Pearson (Alaska Airlines), Manila (Philippine Airlines), and Liberia, Costa Rica (Alaska Airlines). More international connections have already been announced for 2025 with Kelowna (WestJet), Zurich (Edelweiss Air), Copenhagen (Scandinavian Airlines), Seoul (Hawaiian Airlines), and Tokyo–Narita (Hawaiian Airlines). 

Buttressing this growth, the Port of Seattle is marching toward a substantial expansion of the airport. Last fall, the agency released its draft Sustainable Airport Master Plan (SAMP) Near-Term Projects Environmental Assessment. It’s an important milestone as the agency tries to obtain authorization from federal and state partners to approve a lengthy project list, complete design and engineering, and advance toward construction. 

All told, the near-term projects list includes over 30 different project items. Individual project scopes differ wildly, but include airfield improvements, relocating existing facilities through new construction, building new roadways and infrastructure, and creating a brand new terminal. 

The Port of Seattle has an ambitious project list to expand airport facilities, including a brand new terminal to the north. (Port of Seattle)

The near-term projects list was developed with the intent of increasing airport capacity for passengers and cargo while reducing aircraft delays and congestion within a reasonable timeframe, which the SAMP is targeting for 2032. The SAMP suggests that those projects would be able to better accommodate 56 million passengers per year and ensure that the airport operates at a much higher level of service.  

Proposed projects would help the airport reach a Level of Service of B. That’s a considerable improvement over the Level of Service D that the airport has been operating under with existing facilities and demand. However, the trajectory of passenger growth could easily exceed 56 million passengers by the time the project list is completed, eventually leading to lower levels of service than the SAMP suggests. In fact, within five years of completing the near-term list, the Port of Seattle expects to see over 64 million passengers pass through airport facilities.

The new terminal will be north of the existing terminal, situated just to the north of the D and N Concourses. The question, however, is in what form as the Port of Seattle is considering two competing options. One option, which is the preferred alternative, would make the new terminal a standalone terminal. The other option, which is considered the hybrid alternative, would directly connect to the existing terminal but still be a terminal in its own right. 

The preferred alternative would establish a standalone terminal to the north. (Port of Seattle)

The preferred alternative would require relocation of a portion of the North Airport Expressway, fire department, and other support facilities to construct the airside terminal. The expressway itself would be pushed, more or less, to the east to make space for new hardstands and terminal concourses and expanded with two more lanes on some portions. The new structure would be Y-shaped, stretching as far north as the control tower, and contain three stories of space — across 609,000 square feet — to house passenger holdrooms, retailers and restaurants, and other amenities. 

A skybridge from the terminal would provide a direct connection to the N Concourse, post-security. In addition, the new terminal’s check-in, baggage claim, security screening, and 1,350-stall parking garage would be located on the current grounds of the Doug Fox surface parking lot (1,620 stalls) with a skybridge over the expressway to connect to the airside terminal area.

The hybrid alternative would more or less expand the existing terminal facilities northward generally along the airport expressway. (Port of Seattle)

The hybrid alternative requires most of the same relocations as the preferred alternative, but jettisons a few. The airside terminal would be directly connected to the existing terminal, snaking along the realigned expressway to the existing D Concourse. This would require closure of the D Concourse Annex, which currently provides shuttle bus connections to and from planes that serve passengers from remote hardstands. 

As with the preferred alternative, the hybrid alternative would provide a skybridge connection to the N Concourse as well as to the new terminal check-in, baggage claim, security screening, parking garage facility east of the expressway, and 19 gates. It also has the potential for the inclusion of moving walkways within the airside terminal.

Along with both new north terminal alternatives, the Port of Seattle would construct a new passenger ground transportation facility and elevated busway.

The transportation facility would be situated in an area immediately next to the central parking garage and sandwiched between the airport expressway and Link light rail station. The area is currently a paved surface area and was previously conceived as space for a hotel. For passengers, the transportation facility would offer an indoor space with amenities, such as shops and seating, as well as a meeting place to catch shuttles, taxis, ridehails, and chartered services. Passengers would also be able to take shuttle buses from the main terminal to the new terminal and the rental car facility. 

Another benefit is that the Port of Seattle is planning to construct a moving walkway system, which would speed up the walk between the light rail station and main terminal (about a 1,000-foot walking distance). That space would be fully protected from the elements, increasing comfort and decreasing pollution from the neighboring 13,000-stall garage and roadway.