📰 Support nonprofit journalism

Light Rail Work Brings Six Weeks of 1 Line Service Disruptions

Stephen Fesler - May 13, 2024
Passengers at U District Station await as a train pulls in on Northgate Link’s opening day. The system will only get busier at it expands. (Sound Transit)

Sound Transit has kicked off another round of maintenance-related light rail service disruptions on the Link 1 Line. This one will last about six weeks with varying levels of impacts as the agency readies the system for the future East Link and Federal Way extensions, and completes necessary state of good repair work. Doing the work now will create less systemwide impact, rather than doing it after the Lynnwood Link Extension opens on August 30. Service disruptions started on Sunday, May 12 and will extend through Tuesday, June 25.

Sound Transit has put out a handy diagram highlighting the changing service paradigms throughout the spring service disruptions.

Diagrams show the evolving impacts to 1 Line service in May and June. (Sound Transit)

Rail replacement every Tuesday

The largest system impact will start on Tuesday, May 14 to facilitate rail replacement. This will happen every Tuesday, reducing frequency of trains to every 20 minutes after 11:00pm until the end of service, through Tuesday, June 25.

To support tie-in work for the Federal Way Link Extension and extra storage of Link vehicles, service is being significantly affected through Saturday, June 22 in a phased, alternating pattern.

An elevated platform looking south with electronic displays showing destinations.
SeaTac/Airport is temporary listed as the terminus of the 1 Line during six weeks of service disruptions. (Wes Mills)

The first phase of this started on Sunday, May 12 and will continue though Friday, May 31 with mainline 1 Line service terminating at SeaTac/Airport station. Riders wishing to travel between SeaTac/Airport and Angle Lake stations need to transfer to a shuttle train, which is operating every 16 to 20 minutes. After this first phase, the agency is planning to alternate disruptions as so:

  • Saturday, June 1 and through 10:00am on Sunday, June 2, a second phase of impacts will result in no service between SeaTac/Airport and Angle Lake stations. Riders would best served by traveling between the two stations via the RapidRide A Line, which will provide free rides during these periods.
  • Sunday, June 2 through Saturday, June 21, service impacts will revert back to the Airport to Angle Lake shuttle train, like the first phase.
  • Saturday, June 22 service will again terminate at SeaTac/Airport, same as the second phase, with free A Line service to compensate.

Columbia City tile work on June 1 and 2

Separately, Sound Transit will carry out another round of platform tile replacement work in the Rainier Valley. This will be centered on Columbia City, but fortunately involves only two days of work on Saturday, June 1 and Sunday, June 2. Those two days, trains will operate on reduced 20-minute frequencies between Stadium and SeaTac/Airport stations since only one track at a time will be open in and around Columbia City.

Consequently, southbound riders on trains that don’t operate through to SeaTac/Airport will need to get off at Stadium and wait for the next train that does. However, service north of Stadium won’t be impacted this disruption, providing combined 10-minute frequencies.

At Columbia City itself, only one platform will be open at a time, with the northbound platform closed on Saturday, June 1 and the southbound platform closed on Sunday, June 2. Riders will have to use the only open platform for both directions, so they’ll want to be aware which direction a train is going.

Finally, Sound Transit will carry out East Link Extension tie-in work on two days in late June. This will force closure of the Downtown Seattle Transit Tunnel from 10:00pm on Friday, June 21 through the end of service on Sunday, June 23. Shuttle buses will be put into service between Capitol Hill and SoDo stations every 10 to 15 minutes. 1 Line service will operate as essentially two separate lines from those stations to their terminals every 15 minutes.

Later this fall, however, Sound Transit has sketched out potential East Link Extension tie-in work. That could last several weekends in October and November. So, further substantive service impacts are on the horizon and could interfere with the 1 Line in the post-Lynnwood Link Extension environment.

Sound Transit Says 1 Line Headaches Will ‘Smooth Themselves Out’
Facing half-hour headways downtown through February 4, riders are complaining of overcrowding. Seattle’s transit riders still have two full weeks left of planned disruptions to Sound Transit’s high capacity light rail spine, the Link 1 Line. Those disruptions, deemed necessary by Sound Transit to make safety and maintenance upgrades to their downtown Seattle transit tunnel, … Continue reading Sound Transit Says 1 Line Headaches Will ‘Smooth Themselves Out’
How Will Sound Transit Manage Future Service Disruptions with Two Overlapping Lines?
With another “Future Ready” maintenance project coming down the pike in January, it raises a big question for the future: What should riders expect when Sound Transit needs to do planned or emergency maintenance work in the downtown tunnel and elsewhere in the Link system? Starting in late 2025 or 2026, riders can expect the … Continue reading How Will Sound Transit Manage Future Service Disruptions with Two Overlapping Lines?
Late Summer ‘Future Ready’ Maintenance Leads to Link Service Disruptions
Light rail won’t operate between SoDo and Capitol Hill on August 12 and 13, with a service gap bus bridge instead. A series of single-tracking disruptions will follow. More planned service disruptions are coming to the Link light rail. On Thursday, Sound Transit CEO Julie Timm announced upcoming service disruptions to address track quality issues … Continue reading Late Summer ‘Future Ready’ Maintenance Leads to Link Service Disruptions
Sound Transit Decrees ‘Tile-mageddon’ Service Disruptions Due to Maintenance Work
On Tuesday, Sound Transit made a surprise announcement that the agency would be embarking on months of maintenance work on the Link 1 Line in a project dubbed “Future Ready.” Riders, however, may dub the disruption “tile-mageddon,” as relatively mundane maintenance work, like replacing tile pavers, leads to major service reductions, which would have local … Continue reading Sound Transit Decrees ‘Tile-mageddon’ Service Disruptions Due to Maintenance Work